Project Update: MidSouth Community FCU Ops Center

October 18th, 2024

CBI completed last week the third floor decking, roof bar joists, and poured concrete on second floor after inspections at the new Ops Center. Installation of stairs and rails began as well as floor drains at open terrace.

This week at the building site, CBI will be prepping the third floor for concrete, continue bar joist bridging along with miscellaneous steel work, complete the stairs and railings, pour the third floor slab after inspections, and begin metal stud framing at the first floor.

Great progress and go team!