With a solid break in the weather, a busy week of work was completed with more to come following the holiday for Consultants and Builders and MidSouth Community FCU. Thank you for the continued partnership!
All topsoil and subgrade efforts are being managed with continued monitoring of erosion control. The structural fill addition will start next week to enable subgrade finishing and underground storm materials will arrive on site.